Facility
Horse Hollow Wind Energy Center

Project Location
Abilene, TX (Taylor & Nolan Counties)

Commercial On-line Date (COD)
September 2006

Total Capacity
735.5 Megawatts

Annual Energy Production
1,930,000 Megawatt Hours

Horse Hollow Wind Energy Center
Horse Hollow Wind Energy Center

Project Site:

  • The Horse Hollow Wind Energy Center is located in North Central Texas. The facility was constructed on over 47,000 acres in both Taylor and Nolan counties.

Turbines:

  • 291 GE 1.5 megawatt wind turbines and 130 Siemens 2.3 megawatt wind turbines.
  • The GE turbines are over 250 feet tall and have three 126 feet long blades.
  • The Siemens turbines are over 230 feet tall and have three 150 feet long blades.

Project Development:

  • The project was built in three phases. The first phase of 213 megawatts was completed in late 2005, the second phase of 223.5 megawatts was completed in the second quarter of 2006; and, the third phase of 299 megawatts was completed in September of 2006.